National Recreational Trails Grant Approved – May 3, 2013
Friday, May 3rd, the Traildogs received notification of approval for our National Recreational Trails Grant in the amount of $95,000, as requested.
This grant will provide 80% of the $95K, or approximately $74,000, needed to complete the final 5.4 mile section of the trail from Brady Mountain Road to the Blakely Mountain Dam. The 20% matching requirement will be covered by in-kind volunteer support and trail donations.
This eighth addition to the LOViT, when completed, will extend the Trail to its planned 45 miles of developed mountain biking and hiking trail. Our current plan is to begin construction of this final phase in the late fall of this year. We plan to put construction of this section of the Trail out for bids within the next 60 days.
Congratulations to all who have contributed to the eight-year-long effort to develop the Lake Ouachita Vista Trail.